Construction Update

Monarch Construction worked on the following this week: 

New Building Wing

  • Foundation pad and footers for the new wing addition continues
  • Underground storm drain work continues

New Mechanical Room

  • Prepping walls in the new mechanical area

Site Work

  • Installing road way light bases
  • Underground fiber pulls 

Interiors

  • Ceiling grid removal is scheduled for after hours work
  • Beginning demolition of cooling tower and air handles in existing mechanical room